THE VILLAGE

Progress on The Village precinct's construction continues to take shape rapidly.

Civil construction of all current stages within The Village are now complete. Stage 201 has titled and settled.

Stage 202 construction is scheduled to get underway later this year.

Civil construction of the Stage 190 Ison Road Wetland is now complete. Landscaping plans have been finalised and landscaping of the wetland began in April.

Located in Stage 197, the Maywood Road Reserve is now complete and open for families to enjoy. The park includes a playground with a swing set and natural play amenities.

A large double-sided mural sits to the side of the park, designed by local artists VEINS (Christian Vine) and Jenna Oldaker. The artwork was inspired by the biodiversity of Wyndham City and the local indigenous species of Grey, Yellow, and River Red Gums with Kangaroo Grass over Basalt rock formations — all plants and minerals iconic to the area.

 

Construction of the Manor Lakes Boulevard District Reserve continues. Children of all ages will enjoy the basketball and netball courts, fitness equipment, and a small running track, while families can gather by the BBQs with adjoining seating. A dog park will allow pets and owners to socialise beside the creek.

Civil works in the Display Village are now complete and a selection of display homes are now open with several others under construction.

 

LAKESIDE

It's great news for prospective residents of Lakeside, with titles in Stage 160 achieved in early January.